New approach delivers significant carbon savings at National Grid’s Wimbledon substation


National Grid is working with Laing O’Rourke to achieve a significant carbon saving during work to extend a substation in Wimbledon.

25 Apr 2017

New approach delivers significant carbon savings at National Grid’s Wimbledon substation


• National Grid awards first contract with carbon weighting to Laing O’Rourke


• Contract on track to deliver 23% carbon reduction and £3m saving during substation extension project, equating to taking over 7,600 cars off the    

  road for a year

 

 

National Grid is working with Laing O’Rourke to achieve a significant carbon saving during work to extend a substation in Wimbledon.

 

The company awarded the contract for the construction work following a tendering process that factored in a number of environmental targets. As of December 2016, the identified carbon savings have already been met and further savings are expected in the second phase of the project.

 

In addition to reducing the environmental impact of the construction work, this approach brings more value to customers and the end consumer. National Grid is already establishing a strong link between carbon and cost, with the project set to deliver both a 23% reduction in carbon and a £3m saving. This equates to taking 7,600 cars off the road for a year.

 

Modifications to the substation design have made the build more efficient and resulted in carbon savings. Huge savings in sulphur hexafluoride (SF6)were achieved through use of more efficient equipment. 17% fewer piles have been used in the foundations of the substation, and the gas insulated substation building will have a 17% smaller footprint. Firewalls have a reduced thickness which also leads to a reduction in the use of materials and therefore the extension’s carbon footprint.

 

Ian Cartwright, Director of Capital Delivery for National Grid said: “We’ve set ambitious targets to reduce the carbon emissions resulting from our construction work by 50% by 2020 and the Wimbledon project represents an important step to achieving that.

 

“We will include carbon as part of our criteria for investment decisions to enable us to build and maintain a sustainable network for the future. A pilot has already started with an ambitious target to put an internal price on carbon used in all investment decision-making on major projects by 2020.

 

“We estimate that there is potential for us to reduce construction costs through lower carbon design. Our analysis has shown that the lowest carbon suppliers were, on average, 15% lower in cost than those not selected. That is great news for electricity users as they ultimately fund our investment in maintaining and improving our network.

 

Ian added: “Since 2013, National Grid has measured the carbon impact of over 200 schemes, ahead of building work starting. Our engineers have recorded over 7,900tCO2 that they have been able to design out, which is the average annual carbon footprint of over 800 people.”

 

National Grid’s achievements don’t stop there. The company has recently been shortlisted for the Business in the Community (BITC) award in environmental leadership, and the Wimbledon scheme has already won the Edie Sustainability Leaders Award for an innovative approach to carbon management.

 

Laing O’Rourke Project Leader, Lodewyk De Clercq said; “We’re delighted to be working with National Grid and to be operating on this innovative approach to evaluating carbon performance, which has allowed us to engage early with National Grid, finding innovative engineering solutions to complex construction challenges.

 

“We have employed digital engineering, offsite manufacturing and other solutions to work safer, more efficiently, and in a more sustainable manner. Since 2008 Laing O’Rourke’s UK business has halved its carbon emissions thanks to such measures, and it’s fantastic to work alongside like-minded clients such as National Grid, who see both the economic and environmental benefits of sustainable construction."

Contact for media information only

Press officer - Infrastructure Projects
Jeanette Unsworth
jeanette.unsworth@nationalgrid.com
+44 (0)7785 290230

Share this page

Notes for editors


Notes to Editors:

National Grid is one of the largest investor-owned energy companies in the world and was named Responsible Business of the Year 2014 by Business in the Community. This accolade acknowledges all of our efforts in getting involve with the things that really matter to us and to society. We own and manage the grids that connect people to the energy they need, from whatever the source.  In Britain and the north-eastern states of the US we run systems that deliver gas and electricity to millions of people, businesses and communities.

In Britain, we run the gas and electricity systems that our society is built on, delivering gas and electricity across the country.  In the North Eastern US, we connect more than seven million gas and electric customers to vital energy sources, essential for our modern lifestyles.

National Grid in the UK:

  • We own the high-voltage electricity transmission network in England and Wales, operating it across Great Britain
  • We own and operate the high pressure gas transmission system in Britain
  • We also own a number of related businesses including LNG importation, land remediation and metering
  • Our portfolio of other businesses is mainly concerned with infrastructure provision and related services where we can exploit our core skills and assets to create value. These businesses operate in areas such as Metering, Grain LNG Import, Interconnectors and Property. National Grid Carbon Ltd is a wholly owned subsidiary of National Grid. It undertakes Carbon Capture Storage related activities on behalf of National Grid.

Find out more about the energy challenge and how National Grid is helping find solutions to some of the challenges we face at www.nationalgridconnecting.com

National Grid undertakes no obligation to update any of the information contained in this release, which speaks only as at the date of this release, unless required by law or regulation.

Related Photos

Norwich substation

Norwich substation

Tags:Electricity transmission, Substations

Date:01/01/0001
400kV pylon

400kV pylon

Tags:Electricity transmission, Infrastructure, Equipment

Date:01/01/0001
Connecting to life: Annual Report & Accounts 2014/15 front cover

Connecting to life: Annual Report & Accounts 2014/15 front cover

Tags:Annual Report, Electricity distribution, Electricity transmission, Field employees, Infrastructure, Landscape, Safety, Team

Date:04/04/2017

Related Videos

Where Energy Comes From

Where Energy Comes From

Tags:uk, energy, Corporate Videos, gas, National Grid UK, electricity

Date:25/11/2011
National Grid offers T-pylon for the first time in the UK.

National Grid offers T-pylon for the first time in the UK.

Tags:uk, Corporate Videos, electricity, youtube, managing the energy networks, National Grid UK

Date:22/07/2013
The Future of Energy

The Future of Energy

Tags:energy, Corporate Videos, electricity, gas

Date:25/11/2011