National Grid provides update on Visual Impact Provision (VIP) project to reduce the visual impact of overhead lines in AONBs and National Parks


Latest stage of a £500 million project to reduce visual impact of electricity infrastructure in protected landscapes

15 Sep 2015

  • Four locations in England and Wales prioritised by a leading stakeholder group for detailed technical work
  • £24 million initiative for smaller landscape enhancement projects set for Winter launch

Plans to reduce the visual impact of electricity infrastructure in nationally protected landscapes across England and Wales have reached a new landmark, following decisions by the project’s independently chaired Stakeholder Advisory Group.

In November 2014, twelve sections of high voltage lines in eight Areas of Outstanding Natural Beauty (AONBs) and National Parks were shortlisted as having the most significant landscape and visual impact, following a study overseen by leading landscape expert Professor Carys Swanwick.

Since then, National Grid and independent landscape consultants have done further technical work with considerable and highly detailed input from local stakeholders in each location. This has enabled the Stakeholder Advisory Group to prioritise four projects from the shortlist.

The Stakeholder Advisory Group’s decisions were made after a rigorous review of each shortlisted section of line. Members at a two-day meeting considered each project using a set of five guiding project principles from the Visual Impact Provision project’s policy.*

These four projects will be taken forward over the next 12 months for detailed technical feasibility works which will include environmental studies, archaeological studies and engineering work ‘on the ground’. There will also be further significant engagement with local stakeholders and communities.

National Grid transmission lines which have been prioritised in protected landscapes are:

  • Dorset Area of Outstanding Natural Beauty near Winterbourne Abbas
  • New Forest National Park near Hale
  • Peak District National Park near Dunford Bridge
  • Snowdonia National Park near Porthmadog

Using a £500 million allowance made available by Ofgem until 2021, National Grid plans to reduce the visual impact of sections of high voltage overhead lines in these locations. A range of different ways of doing this has been considered in each location.

Given the sensitive nature of these protected areas, replacing existing overhead lines with underground cables has generally proved to be the preferred option both technically and in discussion with local stakeholders.

Chris Baines, Chair of the Stakeholder Advisory Group, said: “Reducing the visual impact of pylons and power lines in our most precious landscapes is highly desirable, but it is also very expensive and technically complex so we have had to make some difficult decisions. Although four schemes have been prioritised, none of the locations on our original shortlist have been dropped and they will remain under consideration for future work to reduce the impact of National Grid’s transmission lines under the Visual Impact Provision project.”

Hector Pearson, Visual Impact Provision Project Manager, National Grid, comments: “This is a unique stakeholder-driven project, and it continues to represent a major opportunity to conserve and enhance the natural beauty, wildlife, cultural and environmental heritage of some Areas of Outstanding Natural Beauty and National Parks. We will continue to work in partnership with stakeholders to not only mitigate the impact of our transmission lines in these areas but to also enhance the landscape, and deliver value for money.”

The Stakeholder Advisory Group is chaired by environmentalist, Chris Baines and comprises senior representatives from organisations including the Campaign for National Parks, Campaign to Protect Rural England, Campaign for the Protection of Rural Wales, Historic England, Cadw, Natural England and the National Trust. It was established to help National Grid identify which transmission lines should be prioritised to make use of the £500 million allowance.

The protected landscapes that have not been prioritised are the Brecon Beacons National Park, High Weald AONB, North Wessex Downs AONB and the Tamar Valley AONB. These locations will remain under consideration for future work using the VIP allowance.

National Grid is also set to use part of the £500 million for smaller localised visual improvement projects which can be accessed by all AONBs and National Parks with existing National Grid electricity infrastructure.

Set to be launched in the Winter, this landscape enhancement initiative will to provide up to £24 million over six years. The aim will be to reduce the visual impact of National Grid’s existing infrastructure in AONBs and National Parks and improve the related visual quality of the landscape. A range of local visual improvement projects could enhance biodiversity, benefit cultural heritage or raise awareness of natural and historic features of a landscape.

Contact for media information only

Head of UK regional media relations - Infrastructure projects
Stewart Larque
stewart.larque@nationalgrid.com
+44 (0)7831 864034
+44 (0)1926 655274

Share this page

Notes for editors

About Visual Impact Provision

All electricity transmission owners are funded by a price control mechanism which is agreed with and set by Ofgem, the electricity and gas markets regulator. Ofgem has agreed a set of price controls and incentives for the period from April 2013 to March 2021. The new price controls and incentives include a provision of £500 million to mitigate the visual impact of existing electricity infrastructure in nationally protected landscapes in Great Britain.

For National Grid, which is the electricity transmission owner in England and Wales, this means considering the visual amenity of our existing infrastructure in National Parks and Areas of Outstanding Natural Beauty (AONBs).

*The project’s guiding principles are to prioritise potential projects which:

  • Result in greatest landscape enhancement benefits
  • Result in greatest opportunities to conserve and enhance natural beauty, wildlife and cultural heritage, whilst avoiding unacceptable environmental impacts
  • Result in greatest opportunities to encourage public understanding and enjoyment of the protected landscapes, including positive socio-economic impacts
  • Are technically feasible in the context of the wider transmission system
  • Are economical and efficient

More information about the Visual Impact Provision project can be found at:
www.nationalgrid.com/vip


Notes to Editors:

National Grid is one of the largest investor-owned energy companies in the world and was named Responsible Business of the Year 2014 by Business in the Community. This accolade acknowledges all of our efforts in getting involve with the things that really matter to us and to society. We own and manage the grids that connect people to the energy they need, from whatever the source.  In Britain and the north-eastern states of the US we run systems that deliver gas and electricity to millions of people, businesses and communities.

In Britain, we run the gas and electricity systems that our society is built on, delivering gas and electricity across the country.  In the North Eastern US, we connect more than seven million gas and electric customers to vital energy sources, essential for our modern lifestyles.

National Grid in the UK:

  • We own the high-voltage electricity transmission network in England and Wales, operating it across Great Britain
  • We own and operate the high pressure gas transmission system in Britain
  • We also own a number of related businesses including LNG importation, land remediation and metering
  • Our portfolio of other businesses is mainly concerned with infrastructure provision and related services where we can exploit our core skills and assets to create value. These businesses operate in areas such as Metering, Grain LNG Import, Interconnectors and Property. National Grid Carbon Ltd is a wholly owned subsidiary of National Grid. It undertakes Carbon Capture Storage related activities on behalf of National Grid.

Find out more about the energy challenge and how National Grid is helping find solutions to some of the challenges we face at www.nationalgridconnecting.com

National Grid undertakes no obligation to update any of the information contained in this release, which speaks only as at the date of this release, unless required by law or regulation.